Please call the Building Department office to schedule an inspection. (refer to inspection hours below)
The following information is required in order to schedule an inspection.
TUESDAY & THURSDAY 7:45 – 11:30AM
TUESDAY & THURSDAY 7:00AM – 7:45AM Plumbing questions will be answered on these days/hours
TUESDAY & THURSDAYS 7:45AM – 11:30AMÂ
MONDAY – FRIDAY 9:30AM – 1:00PM
TUESDAY & THURSDAY 11:00AM – 2:00PM
MONDAY – FRIDAY 9:30AM – 1:00PM
The following are REQUIRED inspections pursuant to NJAC 5:23-2.18 for NEW BUILDINGS, ADDITIONS, RENOVATIONS & ALTERATIONS. Â Â
1. Building:Â Footing bottom of trench, and rebar if applicable PRIOR to the pouring of concrete.Â
2. Electric: Rough wiring for all fixtures and trenches if applicable. Electric finalÂ
3. Mechanical: All duct work, exhaust fans, motors, and dryer vents. Before sheet rock. Mechanical final
4. Plumbing: Rough installation; air test for gas piping, water test for water piping, waste and vent piping and trenches if applicable. Plumbing final
5. Fire: Rough location of all fire protection equipment, including smoke alarms Fire final *Please note all manufactured fireplaces are subject to rough inspection as per the UCC. Â Kitchen hoods over 400 CFM require permit.
Note: Â Zoning approval is not an approval to start building. All drawings must be approved by the required disciplines and a building permit must be issued. Â Other inspections may be required depending on the scope of the project. Consult the Subcode Officials if you have questions.