We are in the final steps of the Linden Avenue roadway improvement project. We recognize that Linden Avenue is a high-traffic area and that construction may cause temporary disruptions. We appreciate your patience and cooperation as we complete these improvements and invest in our roadways. Please continue to follow posted signage and construction notifications, and allow extra time when traveling through the area.
Residents in the directly affected areas will receive additional notifications in their mailboxes, including important information regarding parking restrictions and garbage collection during construction. Garbage/recycling should be placed out the night before.
Milling is scheduled to begin Monday, August 24th.
Milling will begin at Fairview Avenue and continue down Linden Avenue over several days.
Paving is expected to start Wednesday, August 26th.
Milling is scheduled to begin Monday, August 24th
• All cars must be removed from the parking lots by 7:00 AM
• There will be no parking during the day, but you will be able to park overnight Monday and Tuesday.
Paving is scheduled to start Wednesday, August 26th
• All cars must be removed from the parking lots by 7:00 AM
• There will be no parking available overnight. Overnight parking restrictions will be relaxed on surrounding streets
Striping is scheduled to start Thursday, August 27th
• No access to the parking lots until after 2pm
***All dates are weather permitting***
❗❗Register for Township alerts by texting "AlertVerona" to 67283 or register here.
If you are in need of assistance or have questions, please call Public Works during normal business hours 973-857-4805